|
Beijing-Shanghai
High-Speed Line, China
The 1,464km Beijing-Shanghai main
railway line is one of the most important in China, connecting two of
the
country's most prominent economic areas and forming the busiest railway
route.
However, China is currently
upgrading
the line to allow it to handle passenger traffic, as well as heavy
freight
traffic, which currently forms the only traffic on the route. The
Shanghai
Railway bureau is working towards increasing the power supply for the
operation
of passenger trains, but at the same time, the Chinese Ministry of
Railways has
a much bigger project in progress – the 1,318km Beijing-Shanghai
high-speed
line running parallel to the existing route.
"The new Beijing-Shanghai line
is being built to improve journey times and ease pressure on existing
railway
corridors between the two cities."
It will be solely dedicated to
passenger train operation, and the Chinese Ministry of Railways is
promising a
2010 opening date, three years after the scheduled completion of the
115km
Beijing-Tianjin high-speed line.
The new Beijing-Shanghai line is
being built to improve journey times and ease pressure on existing
railway
corridors between the two cities. Construction is expected to take just
five
years.
The Project
The Chinese Ministry of Railways'
initial design work for the high-speed line was completed in June 1998.
Feasibility studies for the new
route were finally approved in March 2006, welcome news as the current
line is
the busiest in China and increasingly a bottleneck. More than a quarter
of the
country’s population lives close to the line, which accounts for 10.2%
of
passenger transport and 7.2% of freight.
The new high-speed line will be
designed for 300km/h (186mph) operation and reduce the journey time
between
Beijing and Shanghai from 14 hours to just five. An estimated 220,000
passengers per day will use the trains.
Despite China wishing to complete
the line by 2010, engineers have said that construction could take at
least
until the middle of the decade. The total cost of the new line is
expected to
be ¥100bn ($12bn). Foreign investment will be allowed.
Infrastructure
Initially, the Chinese Ministry of
Railways was planning to build the high-speed line using only domestic
technology. However, in May 2006, the Ministry opened an invitation to
tender
for contracts to the foreign market, with particular interest in the
German and
French high-speed railway technology. Alstom, Siemens and Japan-based
Mitsubishi-Kawasaki are all said to be interested in tendering for
parts of the
project.
"The rolling stock will feature
an aluminum body and have specially engineered windscreen glass."
The Beijing-Shanghai high-speed
line
will have 24 stations, including Tianjin, Jinan, Xuzhou, Bengbu and
Nanjing.
The alignment is designed for
350km/h operation, although the initial design top speed has been set
at
300km/h (186mph). The Shanghai-Nanjing section of the current main line
was
chosen for early rebuilding to enable testing to take place, largely
because it
crosses the soft terrain of the Yangtse delta, presenting the engineers
with
their most difficult challenge.
Two-thirds of the new route is
expected to be constructed on embankment, with the vast majority of the
remaining third being laid on bridges. Two major river crossings, of
the Yellow
and Yangtse rivers will be needed.
Rolling
Stock
Tests carried out in 1998 using a
modified Shaoshan eight electric locomotive on the Beijing-Zhenzhou
main line
saw the formation reach 240km/h. These laid the foundations for
development of
a fixed-formation 200km/h electric multiple unit.
The prototype vehicle was completed
at Zhuzhou locomotive works in 1999, for testing with six trailer cars
of four
different types, a driving trailer, one double-deck and two single-deck
vehicles, providing a total of 438 seats. Lightweight construction
techniques
allowed the weight of the power car to be kept down to 84t, the first
time a
21t axleload had been achieved on a four-bogied traction unit in China.
Exact details of the trains for the
new high-speed line have not been formulated, but with China's decision
to
allow foreign investment, French or German technology may play a
significant
role. What is known as that the rolling stock will feature an aluminum
body
and have specially engineered windscreen glass, similar to the strength
used in
airplane windscreens, to withstand impacts from birds.
Signaling/Communications
The existing Beijing-Shanghai
corridor is 1,463km long, and equipped with automatic fixed-block
signaling.
The prototype high-speed train is
fitted with an LKJ-93 automatic train protection system, used in
conjunction
with line side equipment to monitor and record train speed. As the
current fed
to the motors can be varied steplessly, the driver is able to maintain
constant
speed automatically.
The Future
The task force investigating
strategies for development of the high-speed line was expected to
complete its
work during 2000, with construction works starting later in the year.
While this has not happened, the
Chinese Ministry of Railways is keen to push the Beijing-Shanghai
high-speed
project forward and is actively encouraging
input from Europe and Japan. It is the template for of a future
12,000km
high-speed railway network in China by the year 2020, an ambitious
target.
www.railnet.com
Top of page
|